if i bake my bridge at about 100 degrees fehrenheit, how long should i do it??? i thought i could bake an hour but i'm not sure :(

however, every ten min., i'm gonna take it out of the oven and weigh it. and of course, i'll be watching it while it is in the oven.
I know i should stop when it starts to warp, but i don't know how long it'll stand in the oven before warping at 100degrees fehrenheit

Re: Elevated Bridge B/C

Posted: March 26th, 2009, 4:33 pm
by geraldatwork
I don't see how this is going do anything other than possibly weakening and warping the bridge. Any weight lost will be gained within 12 hours or less as the wood reabsorbs the moisture due to the relative humidity. You don't want to test the bridge when it is dry as it will break easier.

Re: Elevated Bridge B/C

Posted: March 26th, 2009, 5:22 pm
by sewforlife
You should only bake your bridge for 30 minutes at max. 200 degrees.
So far, my best bridge efficiency is 909. A 1000 is actually pretty easy to achieve, if you can think more strategically.

Re: Elevated Bridge B/C

Posted: March 26th, 2009, 5:26 pm
by jcms science boy
sewforlife wrote:You should only bake your bridge for 30 minutes at max. 200 degrees.
So far, my best bridge efficiency is 909. A 1000 is actually pretty easy to achieve, if you can think more strategically.
well my state is this saturday.... and my max. efficiency is 1000

Re: Elevated Bridge B/C

Posted: March 26th, 2009, 6:18 pm
by cypressfalls Robert
If you have a bridge that weighs 15 grams and holds all the weight(15 kilos Div c) what would the efficeincy be?

Re: Elevated Bridge B/C

Posted: March 26th, 2009, 6:19 pm
by croman74
1,000.

Re: Elevated Bridge B/C

Posted: March 26th, 2009, 6:23 pm
by cypressfalls Robert
What is the equation?
I got 2,000

Re: Elevated Bridge B/C

Posted: March 26th, 2009, 6:31 pm
by croman74
You do Amount held divided by mass of bridge. So:
15000/15=1,000

Re: Elevated Bridge B/C

Posted: March 26th, 2009, 7:05 pm
by bob3443
cypressfalls_Robert wrote:What is the equation?
I got 2,000
2,000??? really?
that's amazingly good....

Re: Elevated Bridge B/C

Posted: March 26th, 2009, 7:10 pm
by smartkid222
bob3443 wrote:
cypressfalls_Robert wrote:What is the equation?
I got 2,000
2,000??? really?
that's amazingly good....
it's not 2000
efficiency= weight held (g) / weight of bridge (g)